Owner Panel: State of the Union – Prefab Adoption in Life Sciences

  • Explore how modular clean rooms are becoming standard practice and why full volumetric modular GMP facilities remain niche but critical for speed-to-market.
  • Discuss time savings of 6–8 months with prefab vs. stick-built solutions and its impact on competitive advantage.
  • Examine supply chain constraints (e.g., HVAC lead times of 50–60 weeks) driving prefab adoption in pharma and healthcare.
  • Highlight hybrid strategies—integrating modular elements within stick-built shells for flexibility and scalability.
  • Consider union and regulatory challenges that complicate full prefab execution in healthcare and life sciences.